16 Mar 2021

MAB Community Update – March 16, 2021

2021-06-15T16:11:56-04:00March 16th, 2021|

Hello to MacArthur Beach Residents!
Our regular March board meeting was a busy one – long and productive. A welcome to Ann Sullivan who has agreed to join the board.
Our insurance agent attended to discuss our rates and what we might do to reduce them. We are starting a wind mitigation study on the […]

1 Feb 2021

MAB Community Update – February 19, 2021

2021-06-15T16:15:19-04:00February 1st, 2021|

Hello to MacArthur Beach Residents!
Since I know that many of you cannot be here nor can you attend the monthly board meetings, I will try to keep you posted.
We had a large unexpected insurance increase for 2021. Many associations in Florida have experienced the same. We have employed Karins Engineering to give us […]

30 Oct 2020

Tom’s Update – October 30, 2020

2020-10-30T17:03:13-04:00October 30th, 2020|

To All,

All of the new railings have been installed on the High rise and Artistry Painting has a 20 foot section from the ground up on the building to do and will be completed by next Wednesday.

The painters have started to pressure clean the Mid rise as we speak, which hopefully the […]

30 Oct 2020

2020 Cable Information & Survey

2020-10-30T17:01:33-04:00October 30th, 2020|

Dear MacArthur Beach Members,

This is a reminder to return your completed surveys, as soon as possible, we would like to have them tallied for the Board Meeting on Friday, November 6, 2020.

CLICK HERE to view the new proposed contract information and survey package prepared by the […]

9 Oct 2020

Tom’s Update – October 9, 2020

2020-10-09T14:24:32-04:00October 9th, 2020|

To All,

We are making great progress on the High/Mid-rise painting project. Artistry Painting is almost 3/4 of the way done with the High rise and will start the Mid rise in about 2 weeks.

The 37 and 38 sections of the High rise have the new railings installed and the 5th floor to […]

22 Sep 2020

Tom’s Update – September 22, 2020

2020-09-22T17:37:57-04:00September 22nd, 2020|

To All,

The High rise painting project is going well, however, we ran into an issue of taking the 40 year old railings off. What we found, and this is hit and miss on different lanai’s, is spalling (bad concrete). With the both contractors tight schedule and time enough to fix issues, this is […]

28 Aug 2020

Tom’s Update – August 28, 2020

2020-08-28T16:01:32-04:00August 28th, 2020|

To All,

Artistry Painting is just about done setting up the swing stage on the west side of the High rise and will paint the building clock wise. They will pressure clean first then paint.

The new railings arrive today and will be installed a side at a time. If you have furniture out […]

31 Jul 2020

Tom’s Update – July 31, 2020

2020-08-28T16:01:25-04:00July 31st, 2020|

To All,

With window and painting projects there are a lot of moving parts that have to happen to keep the momentum moving forward. All 30 windows have been installed in the Mid rise building and only
4 left to stucco on the outside and 6 left to touch up on the inside. Thankfully we […]

10 Jun 2020

Tom’s Update – June 10, 2020

2020-06-10T15:26:41-04:00June 10th, 2020|

To All,

Starting on June 22, we will begin to install the windows in the Mid rise buildings and it should take a couple of weeks to install all of them. As it stands now we will begin installing the new railings for the High rise the first week in July.

With those two […]

7 May 2020

Tom’s Update – May 7, 2020

2020-05-11T12:24:01-04:00May 7th, 2020|

To All,

On Tuesday the high rise transformer shorted out and not sure why it did. F.P.L. installed a temporary line and will be back Monday 5/11/20 to install a new underground line at no cost to us.There should be no power outage while this is being done.

We have changed pest control companies […]